top of page
Search

Lunar Temporary Works

Sep 28
18 min read

Updated: 7 days ago

A lunar landing pad, habitat, road, power system or surface facility is normally presented in its completed configuration. However, construction does not begin there.



Before the permanent work can be placed, assembled or commissioned, the site must function as a construction site. Equipment needs ground on which it can travel and operate. Materials and components need places to be received, staged and handled. Excavated or graded regolith needs somewhere to go. Construction plant needs access, operating space, power, communications and provision for maintenance and recovery. Temporary excavations, slopes and berms may need to remain stable while other work proceeds.


Here on Earth, many of these functions are provided by temporary works and temporary construction facilities. They may include working platforms, haul and access roads, staging and laydown areas, temporary slopes and excavations, spoiling areas, drainage and ground-control measures, temporary utilities, survey control, equipment pads and temporary support systems. Established construction practice treats these as planned and controlled parts of project delivery, even though many disappear before the permanent asset enters service. UFGS practice, for example, separately addresses temporary construction facilities and controls, earthworks, quality control, submittals and construction records.


The lunar equivalent deserves the same engineering attention, but it cannot simply reproduce terrestrial specifications. Reduced gravity, vacuum, temperature extremes, abrasive regolith, remote or autonomous equipment operation, communications constraints and limited equipment redundancy alter both the design conditions and the consequences of failure. The terrestrial value lies instead in the construction functions: define what is required, establish the applicable ground and operational criteria, prepare the work, inspect and verify it, release it for use, monitor its performance and respond when conditions depart from the accepted envelope.


A 20 m landing pad, for example, is not only a 20 m construction problem. The construction operation may require access and circulation routes, working areas, equipment stand-off and maneuvering space, material staging, regolith handling areas, temporary power and communications, survey control and provision for disabled-equipment recovery. Some of those areas may impose more demanding short-term ground requirements than portions of the completed facility.


For the first lunar construction projects, temporary work may determine where construction equipment can operate, in what sequence the work can proceed, and whether the permanent asset can be built at all.


What are Lunar Temporary Works?

Temporary work is the work and facilities required to execute construction, but which do not necessarily form part of the completed asset. On a lunar site, the definition should remain functional. The idea is not whether an element is permanent or temporary by duration alone, but what construction function it performs and what conditions are required for it to perform safely and reliably.


Terrestrial construction practice already separates temporary construction facilities and controls from permanent works. UFGS 01 50 00 addresses temporary facilities, utilities, controls, staging and site organization, while UFGS 31 00 00 addresses excavation, subgrade preparation, fill, compaction, embankments and surplus material. The lunar application changes the physical and operational conditions, but the construction functions remain recognizable.


For an early lunar project, temporary works can be grouped as follows.

Temporary-work function

Lunar construction examples

Principal construction requirement

Access and circulation

Construction access routes, haul routes, equipment circulation areas, turning and passing areas

Trafficable ground, suitable geometry, maintained operating surface

Working areas

Excavator/dozer operating areas, lifting or handling pads, equipment platforms

Bearing response, deformation control, level/grade tolerance, equipment stability

Staging and assembly

Laydown areas, component staging, assembly areas, payload receiving areas

Prepared surface, defined load capacity, survey control, access

Material management

Regolith stockpiles, excavated-material areas, selected-material storage, processing feed areas

Stable stockpile geometry, segregation, controlled placement and retrieval

Temporary earthworks

Cuts, ramps, temporary slopes, berms, trenches and local fills

Excavation stability, slope geometry, erosion/ejecta considerations where applicable, geometric control

Construction services

Temporary electrical distribution, communications, navigation/localization infrastructure and construction survey control

Availability, protection, redundancy and controlled interfaces

Equipment support

Parking, maintenance, charging/refueling where applicable, inspection and recovery areas

Accessible and stable operating ground, equipment clearances, recovery access

Control and protection

Exclusion areas, stand-off zones, protected routes and temporary barriers/berms

Defined boundaries, survey/location control and compatibility with construction operations

These elements should not be considered independently. A haul route terminates at a working area. A working area connects to a laydown or material-processing area. Additionally, excavated regolith requires transport, temporary storage and possibly processing before reuse, and equipment operating at any of these locations requires power, communications, localization and a means of withdrawal or recovery. The resulting arrangement is therefore a temporary construction system occupying and modifying the ground around the permanent works.


Some temporary work may eventually remain. An access route could become part of the permanent road network. A prepared working platform could later receive equipment or another facility. A berm initially constructed for an active construction operation might be incorporated into the final site configuration. Conversely, other areas may be abandoned, regarded or reclaimed after their construction function ends. Their initial classification as temporary work concerns their role during construction, not necessarily their final physical disposition.


That also affects design. A temporary haul route does not automatically require the same performance criteria as a permanent lunar road, nor does a construction working platform necessarily use the same acceptance criteria as the foundation area for the permanent asset. The required performance follows the construction load, equipment, duration, consequence of loss of function and ground response associated with that particular use.

This is where temporary work becomes a geotechnical problem as well as a construction-planning problem. The lunar site cannot be represented only by the geometry of its completed facilities. It also needs the ground required to build them.


Figure 1. Permanent Asset Footprint vs. Construction Footprint. Conceptual plan view illustrating how the area required to construct a lunar facility extends beyond the permanent asset itself. The construction footprint includes access and haul routes, working platforms, equipment circulation, laydown and assembly areas, regolith stockpiles, material processing, temporary power and communications, equipment recovery areas, and survey control points. Layout is conceptual and not to scale.
Figure 1. Permanent Asset Footprint vs. Construction Footprint. Conceptual plan view illustrating how the area required to construct a lunar facility extends beyond the permanent asset itself. The construction footprint includes access and haul routes, working platforms, equipment circulation, laydown and assembly areas, regolith stockpiles, material processing, temporary power and communications, equipment recovery areas, and survey control points. Layout is conceptual and not to scale.

The Construction Footprint

The permanent asset occupies only part of the area required to build it. A lunar construction site will also need space for access, equipment movement, material handling, temporary storage, processing, servicing, survey control and recovery operations. These functions expand the operational area well beyond the final facility boundary.


For construction planning, it is useful to distinguish between two footprints:

Footprint

Definition

Typical contents

Permanent asset footprint

Area occupied by the completed infrastructure

foundations, structures, pads, permanent roads, utilities and operational facilities

Construction footprint

Area required to execute the work

access routes, working platforms, circulation areas, laydown, stockpiles, processing areas, temporary services, recovery areas and survey/control points

Figure 1 illustrates this distinction conceptually. The construction footprint is not simply a buffer around the permanent asset. Its geometry depends on the sequence of work, equipment dimensions and turning requirements, haulage paths, material flow, temporary loading, maintenance access and the location of temporary support systems.


In transit corridor projects, temporary construction facilities and controls are planned as part of site organization rather than treated as incidental space. UFGS 01 50 00 addresses temporary facilities, controls, utilities and staging, while earthwork specifications address excavation, fill, subgrade preparation and material handling. The same planning is applicable to lunar construction, although the equipment, environment and verification methods will differ.


A buildable asset location is not necessarily a buildable construction site.


Construction Area Is Driven by Operations

The required footprint will change with the construction method. Therefore, a project dominated by excavation and grading will require haulage routes, stockpile areas and equipment maneuvering space. A project involving prefabricated modules may require larger laydown, positioning and assembly areas. A landing-pad project could require extensive material processing and placement areas even though the finished pad geometry is relatively simple.


The size of the construction footprint therefore follows the means and methods used to deliver the assets.

This has consequences for early site selection. A location may be acceptable for the permanent structure but poorly suited to the surrounding construction operations. Nearby steep ground, blocky terrain, crater rims, soft or highly disturbed regolith, restricted access or unfavorable material-handling distances may constrain the work even when the final facility location itself appears suitable. Moreover, the site investigation should therefore extend beyond the final foundation or pad footprint.

Different Areas Carry Different Ground Demands

Not every part of the construction footprint requires the same ground condition.

A laydown area carrying relatively static loads may tolerate a ground response that would be unsuitable for a heavily trafficked haul route. A recovery area may experience infrequent use but must remain accessible under an abnormal operating condition. A working platform may require tighter deformation control because equipment stability or positioning accuracy depends on the supporting ground.


The construction footprint should therefore be divided into functional ground zones, each with its own loading condition and performance requirement.


A practical recommended concept is:

Functional zone

Dominant demand

Access/haul route

trafficability, rutting resistance, repeated loading

Working platform

bearing response, deformation, level and slope control

Laydown/assembly area

bearing capacity, settlement, geometric stability

Stockpile area

ground bearing, slope stability, material segregation

Processing area

concentrated loads, vibration, settlement tolerance

Recovery area

access under abnormal conditions, traction, ground reaction

Temporary service area

stability of equipment supports and protected routing

This zoning also provides a basis for inspection and release. Instead of applying one generalized site criterion, each area can be checked against the function it is expected to perform.


The Construction Footprint Will Move

The construction footprint should not be treated as static. This means that all access routes may be extended. Stockpiles may relocate. Working platforms may be enlarged or abandoned. Temporary service points may shift as construction progresses. Areas used for excavation support may later become material-handling zones, and some temporary works may be incorporated into the final site.


This creates a requirement for configuration control at construction scale. The accepted condition of the site should correspond to the actual stage of work, not to a single fixed masterplan prepared before mobilization.


For lunar construction, where field adjustment may be executed remotely or autonomously, the current configuration of access routes, usable work areas, exclusion zones and recovery paths will need to remain known and controlled.


The construction footprint is therefore both spatial and operational. It defines where construction can occur and under what ground and access conditions it can continue.


Ground performance should be linked to use

For temporary works, the design basis should start with the construction operation and work back to the required ground response.

Temporary-work function

Ground demand

Potential loss of function

Typical verification need

Working platform

bearing resistance, limited deformation, local stability, surface geometry

excessive settlement, tilt, punching, loss of equipment stability

surface level, ground condition, deformation response, local proof or operational verification

Access/haul route

trafficability, traction, repeated-load resistance, grade and crossfall control

rutting, immobilization, route degradation, loss of productivity

surface condition, route geometry, repeated-pass performance

Laydown/assembly area

support of stored components and handling equipment

differential settlement, loss of alignment, unstable storage

bearing condition, surface tolerance, settlement observation

Stockpile/spoil area

surcharge resistance, local slope stability, suitable founding surface

bearing failure, excessive settlement, pile instability

foundation condition, pile geometry, displacement

Material-processing area

concentrated equipment loads, vibration, repeated operating loads

equipment misalignment, local settlement, unstable support

platform geometry, foundation response, equipment tolerance

Recovery area

traction, bearing response, access under abnormal loading

inability to recover disabled equipment, secondary immobilization

access condition, available ground reaction, recovery-path condition

The verification method will depend on the equipment and the maturity of the construction system. At an early stage, this may involve a combination of measured ground properties, controlled trial passes, deformation monitoring and equipment-response data rather than a single acceptance number.


Bearing capacity alone is not enough

A platform can remain well below a classical bearing-capacity failure and still be unsuitable for construction use.


Excessive settlement, local deformation, progressive rutting or differential movement may be sufficient to prevent equipment from operating within its allowable geometry. For lifting, positioning, grading, drilling or assembly operations, serviceability may govern before ultimate ground failure is approached.


Construction platforms and crane operating areas are routinely checked for both load distribution and deformation. In one of the terrestrial project examples available in the SpaceGeotech source set, temporary crane loading, working-platform effects and construction traffic were assessed explicitly as geotechnical load cases rather than assumed to be covered by the permanent design.


The lunar equivalent should follow the same logic: identify the imposed construction load, define the acceptable response, and verify the prepared ground against that requirement.


Repeated loading changes the ground condition

A route that is initially passable may degrade after repeated loaded passes. Local shearing beneath wheels or tracks can alter density and surface form. lose material may migrate into wheel paths. Rutting can change crossfall and steering response. Turning and braking areas can experience more severe disturbance than straight sections.


For lunar equipment, these effects should be considered together with wheel or track geometry, contact pressure, slip, drawbar demand and vehicle mass under reduced gravity. The interaction is an equipment-ground system, not a property of the soil alone.

This has two consequences for temporary works planning.


First, acceptance should not necessarily be based only on the initial condition. Some areas will require performance criteria during use.


Second, maintenance must be part of the temporary work plan. Regarding, recompaction where technically applicable, surface replacement, local reinforcement or rerouting may be required as the construction sequence advances.


Geometry is part of ground acceptance

For construction equipment, the shape of the prepared ground can be as important as its strength.


Relevant geometric controls may include:

  • longitudinal grade;

  • crossfall;

  • local surface irregularity;

  • rut depth;

  • transition geometry;

  • turning radius;

  • edge clearance;

  • platform level tolerance;

  • stockpile setback;

  • excavation and slope geometry.


These parameters should be defined from the operating limits of the equipment rather than from generic roadway or earthworks criteria.


A platform supporting a positioning operation may require tighter tolerances than an access route. A recovery area may require a flatter and more predictable surface than a normal circulation zone because recovery loads can already be close to available traction or ground-reaction limits.


Ground variability has to be carried into the temporary-works design

Lunar regolith is not expected to behave as a uniform engineered fill simply because the surface appears visually consistent.


Differences in density, particle-size distribution, block content, disturbance, local slope, crater ejecta, regolith thickness and underlying material can influence equipment response over relatively short distances. A construction footprint extending well beyond the permanent asset therefore increases the area over which ground variability must be understood.


The required level of characterization should follow the construction consequence. A low-load staging area may justify a different investigation and verification effort from a high-load working platform or constrained recovery route.


This is where the site investigation, construction layout and equipment plan need to be developed together. The ground model should support the areas in which construction will actually occur, not only the final foundation footprint.


Figure 2. Temporary-works ground-performance concept adapted from terrestrial construction practice. Terrestrial crane-platform and construction-traffic loading illustrate how temporary works are treated as explicit geotechnical load cases. Lunar applications would require project-specific equipment loads, ground-response criteria and verification thresholds; the normalized lunar envelopes shown are conceptual only.
Figure 2. Temporary-works ground-performance concept adapted from terrestrial construction practice. Terrestrial crane-platform and construction-traffic loading illustrate how temporary works are treated as explicit geotechnical load cases. Lunar applications would require project-specific equipment loads, ground-response criteria and verification thresholds; the normalized lunar envelopes shown are conceptual only.

Figure 2 adapts this logic into a conceptual ground-performance framework for lunar temporary works. the values themselves are not transferable to lunar construction. The useful precedent is the design logic:


  • temporary equipment loading is defined;

  • the load-transfer system is defined;

  • the supporting ground is assessed;

  • deformation is calculated or measured;

  • operating consequences are considered;

  • the platform arrangement is modified where required.



Working Platforms and Equipment Operating Areas

Working platforms deserve separate treatment because they carry a concentrated part of the construction risk. Their function is not simply to provide a flat surface. They provide the ground interface on which equipment must remain stable, maintain geometry and execute work within operational limits.


For lunar construction, a working platform could support excavation equipment, lifting or positioning systems, drilling units, material-processing equipment, assembly operations or other heavy construction plant. The required performance will depend on the equipment configuration and the task being performed.


The platform is part of the equipment-ground system

A working platform should be treated as a designed interface between the machine and the supporting ground.


The relevant inputs include equipment mass, wheel or track geometry, contact area, load distribution, dynamic effects, eccentric loading, operating radius where applicable, travel mode, repeated loading, allowable tilt and the consequences of differential movement.

The ground-side inputs include density, stiffness, shear resistance, particle size and block content, local layering, regolith thickness, slope, disturbance and the condition of the prepared surface.


These two sets of variables define the operating condition together.

A platform may satisfy an ultimate bearing-capacity check and still be unsuitable if differential deformation exceeds the equipment tolerance. This is especially important where construction operations depend on position, level or alignment.


Examples may include:

Operation

Platform sensitivity

Excavation

local rutting, machine pitch and loss of digging geometry

Lifting/placement

differential settlement, tilt, local punching

Drilling

verticality, vibration, support stiffness

Assembly

level tolerance, settlement beneath supports

Material processing

concentrated loading, equipment alignment, vibration response

Recovery operations

traction, reaction force, approach stability

For some temporary works, direct operational verification may provide more useful information than relying on one inferred geotechnical parameter. A prepared haul route, for example, could be evaluated through controlled trafficking while measuring sinkage, slip, rut development and machine response. A working platform could be checked through a controlled load or equipment positioning operation while monitoring displacement and tilt.


This does not remove the need for site characterization. It provides another layer of evidence between the ground model and release for construction use. The terrestrial monitoring philosophy in the project source set follows the same general approach: predictions are checked against measured response, and the monitoring program is used to confirm whether field conditions remain within the assessed range.


Acceptance at initial preparation does not guarantee continued suitability.

Repeated trafficking, excavation adjacent to the platform, stockpile loading, local disturbance or surface degradation may alter the supporting condition. A platform that was acceptable during one stage of construction may require reinspection before a more demanding operation begins.


Equipment Recovery Has to Be Designed Into the Site

A disabled vehicle or item of construction plant may block access, interrupt material flow, occupy a working platform, or isolate another part of the site. If the fleet is small, the operational effect can be disproportionate to the size of the incident. If the disabled machine has lost mobility because of poor traction, excessive sinkage or local ground failure, the assisting machine may encounter the same condition when approaching. Recovery can then produce a second immobilized vehicle rather than resolving the first.


A vehicle operating routinely may apply relatively predictable wheel or track loads. Recovery can introduce high drawbar forces, uneven wheel reactions, eccentric loading, transient load transfer and substantial slip. The ground condition accepted for normal traffic may therefore be inadequate for recovery.


A recovery zone or pull position may need stronger ground, lower slope, larger maneuvering space or a different surface treatment from the adjacent haul route.

This is one reason to identify recovery areas in the construction layout rather than assume recovery can occur anywhere.


Temporary Works Through the Construction Sequence

Temporary works change as the job advances. Access, working areas, stockpiles, service locations and recovery provisions will not remain fixed from mobilization through completion. The temporary-works plan should therefore be linked to the construction sequence rather than treated as a static site arrangement.


A practical lunar temporary-works sequence can be adapted from established infrastructure-construction practice as follows:

Construction stage

Temporary-works focus

Stage 1 - Establish control and initial access

survey control, route definition, initial communication coverage, first equipment operating areas

Stage 2 - Prepare operating ground

working platforms, route formation, localized grading, temporary slopes and equipment pads

Stage 3 - Establish staging and material handling

laydown areas, stockpiles, processing areas, temporary services and recovery provisions

Stage 4 - Execute permanent earthworks and construction

haulage, excavation, placement, assembly, temporary support, progressive platform modification

Stage 5 - Maintain and reconfigure temporary works

route maintenance, relocation of stockpiles, expansion or closure of working areas, equipment-access changes

Stage 6 - Remove, repurpose or incorporate

demobilization, regrading, conversion of selected temporary areas into permanent infrastructure, final records

This sequence is deliberately construction-oriented. It treats the site as something that is progressively established, used, modified and eventually handed over.


Initial access comes before production

The first construction activity is not necessarily excavation or grading. Before production begins, the project may need to establish a controlled route into the work area, verify that equipment can traverse it, define survey control, confirm communications coverage and prepare the first stable operating surface. The amount of initial preparation will depend on the natural ground condition and the equipment selected.


This creates an early decision point: what minimum temporary infrastructure is required before the main construction fleet can operate?


For some sites, the answer may be limited to route marking and local grading. For others, a prepared access corridor and initial working platform may be required before heavier plant can enter.


However, temporary works planning becomes inefficient when the sequence is defined without considering material movement. Excavation, haulage, stockpiling, processing and placement need to be arranged as one production system.


If the processing area is poorly located, haul distances increase. If stockpiles block future access, they must be moved. If a working platform occupies the only practical route for later equipment, the site has to be reconfigured. it is important to consider that these are construction-layout decisions rather than permanent-design issues, but they can control productivity.


The Temporary-Works Plan

The temporary-works plan should bring the preceding requirements into one controlled construction package. It should define what temporary works are required, where they are located, what ground condition is required, how they are prepared, how they are verified, who can release them for use, how their condition is monitored, and what happens when the configuration changes.


The existing source register supports this overall construction-control structure through temporary facilities, earthworks, QC, submittals, closeout, commissioning, survey control, acceptance, hold points and change management.


A suggested lunar temporary-works plan could include the following:

Plan element

Required content

Temporary-works inventory

access routes, working platforms, staging areas, stockpiles, processing areas, recovery areas, temporary services

Design basis

equipment loads, ground assumptions, geometry, operating limits, service duration

Ground requirements

bearing response, deformation, trafficability, slope, surface tolerance, local stability

Construction sequence

order of establishment, use, modification and removal

Survey and control

coordinates, levels, control points, machine-guidance reference

Inspection and verification

testing, survey, proof loading, trial passes, telemetry or other evidence

Acceptance and release

criteria, hold points, authority and operating status

Monitoring and maintenance

degradation indicators, trigger levels, inspection frequency, repair requirements

Recovery provisions

access, assisting equipment, operating envelope, alternate route

Change control

reconfiguration, changed use, revised loads, deviations and re-release

Disposition

removal, abandonment, regrading or incorporation into permanent works

Records

as-built configuration, test results, releases, restrictions, repairs and final status

The plan does not need to prescribe one universal method for every temporary work. A haul route, processing pad and recovery area will not use the same acceptance criteria. The control structure should be common; the engineering criteria should follow the intended use.


Recommendations for Artemis

Artemis is moving from individual surface missions toward an architecture that includes mobility, logistics, power, communications, ISRU and infrastructure support. NASA already treats these as interacting sub-architectures and has identified gaps in integrated lunar logistics and uncrewed surface mobility. NASA is also developing technologies for roads, landing pads, berms and other lunar surface infrastructure.


For Artemis surface construction, temporary works should be treated as an identifiable engineering package. That package does not require a new lunar construction code before work can begin.


It requires construction requirements, defined interfaces, verification methods and decision authority such as:


  1. Investigate the construction footprint, not only the permanent asset footprint. Site characterization should cover the ground on which construction equipment will travel, turn, work, stage material and recover disabled plant. A technically acceptable landing-pad or habitat location is not sufficient if the surrounding construction area cannot support the equipment and sequence required to build it.

  2. Define ground acceptance criteria by construction function. Haul routes, working platforms, processing pads, laydown areas and recovery zones should not inherit one generalized ground criterion. Each needs a defined operating envelope based on equipment loading, deformation tolerance, trafficability, slope, geometry and consequence of loss of function. Terrestrial temporary works already use this logic: temporary crane-pad and traffic loading are treated as explicit geotechnical load cases rather than assumed to be covered by the permanent design.

  3. Establish formal release of temporary works before equipment use. Prepared ground should carry an operating status such as accepted, accepted with restriction, hold, or closed for maintenance. Release should be supported by appropriate evidence: survey, ground measurements, trial trafficking, proof loading, equipment telemetry or combinations of these methods. This is a construction-control function, not simply a soil-characterization exercise.

  4. Make equipment recovery a design requirement. Artemis surface plant should not be deployed on the assumption that immobilization will be solved operationally after it occurs. Recovery access, assisting equipment, traction and ground-reaction requirements, maneuvering space, alternate routes and abort conditions should be established before production operations. For a small lunar fleet, one immobilized machine can affect several dependent construction activities.

  5. Demonstrate the temporary-works system on Earth before committing it to lunar production. Test programs should include more than individual vehicle mobility. They should reproduce the construction sequence: route preparation, repeated loaded trafficking, working-platform preparation, stockpiling, material transfer, equipment positioning, degradation, maintenance and recovery. Acceptance criteria should be exercised during those demonstrations. NASA already uses Earth testing and lunar demonstrations as part of its surface-technology development pathway; temporary works can be incorporated into that existing approach rather than requiring an entirely separate program.

  6. Maintain a controlled digital construction configuration. The current location and status of haul routes, accepted operating areas, stockpiles, temporary utilities, survey control, restricted zones and recovery paths should form part of the active site model. This becomes especially important where construction is performed autonomously or supervised from Earth. Terrestrial practice already links survey control, machine guidance and grade control to construction acceptance; lunar construction will require the same functions with different execution methods.

  7. Integrate temporary works into Artemis logistics, mobility and infrastructure decisions now. NASA's present architecture already recognizes Infrastructure Support, Logistics Systems and Mobility Systems as distinct but interacting functions, and the agency has acknowledged gaps in surface logistics and uncrewed mobility.

Do not qualify only the lunar asset. Qualify the construction system that will deliver it.

That means demonstrating that the selected site, ground, equipment, temporary works, material flow, recovery provisions and acceptance process can operate together before the permanent infrastructure depends on them.


NASA's Moon to Mars architecture is explicitly intended to grow through progressively more capable lunar operations. NASA The corresponding construction practice should mature in the same way: first establish the ground, temporary works and operating envelope; then release the equipment and work; then build the permanent asset.

For Artemis, the first engineered lunar infrastructure may not be the landing pad, road or habitat. It may be the construction site required to build them.

References

  1. U.S. Army Corps of Engineers, NAVFAC, and AFCEC. UFGS 31 00 00 – Earthwork. Whole Building Design Guide. Covers excavation, subgrade preparation, fill, compaction, embankments, surplus material and earthwork testing.

  2. U.S. Army Corps of Engineers, NAVFAC, and AFCEC. UFGS 01 45 00 – Quality Control. Whole Building Design Guide. Covers preparatory, initial and follow-up control, testing, deficiencies, rework, completion inspection and QC documentation.

  3. U.S. Army Corps of Engineers, NAVFAC, and AFCEC. UFGS 01 50 00 – Temporary Construction Facilities and Controls. Whole Building Design Guide. Principal reference for temporary facilities, site controls, utilities, staging and temporary site organization.

  4. U.S. Army Corps of Engineers, NAVFAC, and AFCEC. UFGS 01 33 00 – Submittal Procedures. Whole Building Design Guide. Used for the construction-control concepts of submittals, deviations, certifications, test reports and approvals.

  5. U.S. Army Corps of Engineers, NAVFAC, and AFCEC. UFGS 01 78 00 – Closeout Submittals. Whole Building Design Guide. Supports as-built records, QC documentation and construction closeout.

  6. U.S. Army Corps of Engineers, NAVFAC, and AFCEC. UFGS 01 91 00.15 – Building Commissioning. Whole Building Design Guide. Relevant to verification, deficiencies, acceptance and handover concepts.

  7. Federal Highway Administration. Field Materials Manual, 2021. Provides terrestrial practice for material acceptance, verification, sampling, earthwork testing, density and construction QA/QC responsibilities.

  8. Federal Highway Administration. Construction Program Management and Inspection Guide. Provides construction inspection, QC/QA organization, earthwork quality-control planning, documentation and acceptance practices.

  9. California Department of Transportation. Construction Manual, Section 4-19 – Earthwork. Relevant to earthwork inspection, embankment preparation, compaction verification, borrow materials and testing practice.

  10. California Department of Transportation. Construction Manual, Section 6-1 – Sample Types and Frequencies. Provides a useful terrestrial basis for acceptance frequency and scaling verification effort with construction production.

  11. California Department of Transportation. Construction Manual, Section 3-5 – Control of Work. Relevant to survey control, grade control, automated machine guidance and maintenance of the construction control network.


Roberto de Moraes

Lunar Construction Strategist | Author | SpaceGeotech




 
 
 

Comments


“All opinions and contributions are independent and educational in nature. SpaceGeotech.org is not affiliated with employer or any commercial service offering.”

© 2025 by Space Geotech. Powered and secured by Wix

  • Vimeo
  • Facebook
  • Twitter
  • YouTube
  • Instagram
bottom of page